The Megawatt Has a Passport Now

Passport

Yingying Li

Six weeks ago, the hard question in Southeast Asian data centres was where to find the power. Today it is who is allowed to use it, and for what.

In early October I wrote down a single sentence to anchor how I read this market: power is the bottleneck, not land and not chips. I still believe the first half. The second half has aged badly.

Between 7 October and 17 November, the most consequential decisions about data centres in Singapore, Johor, Batam and Jakarta were not made by utilities or developers. They were made by trade ministers, an energy minister with a grievance, and officials in Washington drafting a licensing rule most operators in the region have not read yet.

Here is what moved, and what I think it means.

Washington is drawing a line around the compute, not the country

According to reporting by The Information on 12 November, the US Commerce Department is weighing licence requirements for exports of Blackwell-class and more advanced chips to Malaysia, Singapore, Thailand and Indonesia, along with Brazil, Norway and South Africa. The stated target is not these countries themselves. It is Chinese firms renting compute in their data centres from a distance.

The rule is still a proposal, in interagency review. But the same week, Jensen Huang resigned as Nvidia’s CEO, removing one of the loudest voices in Washington against tight restrictions. Ong Kian Ming, Malaysia’s former deputy trade minister, expects Malaysia to absorb most of the hit. Maybank’s analysts warn that Chinese demand for regional compute could fall. Marsh, more measured, expects “more selectivity, rather than a broad retreat.”

I lean towards Marsh. The capital is not going to walk away from the region. What changes is what an operator has to know about its tenants. If this rule lands, tenant due diligence stops being a compliance checkbox and becomes part of the product. The operators who can explain, in plain language, who is running what on their floors will keep the best customers. The ones who can’t will find out what a licence delay does to a lease.

The question a data centre has to answer is no longer “how many megawatts?” It is “whose workloads, on whose chips, under whose rules?”

Malaysia stops subsidising the wait

On 15 October, Malaysia’s trade minister told Parliament that data centre investors will pay for their own transmission upgrades and for every megawatt they reserve, whether or not they use it. No subsidy. Gas costs passed through at market price. At least 30% local content per facility, and mandatory water recycling.

The numbers behind that statement explain the mood. TNB has 8.35 GW of maximum demand under supply agreements, 5.65 GW already connected, and about 1.26 GW of actual data centre load as of June. Roughly 4.4 GW sits reserved and idle. For two years, holding a power allocation was cheap and selling it later was the business model for more than one developer. That window is closing.

Then Google announced US$15 billion for Malaysian campuses in 2027 and 2028, with a pledge to pay 100% of its power and grid-connection costs and to add over a gigawatt of clean energy to the national grid. Whether or not that was choreographed, it reset the benchmark for what a good tenant looks like. Every mid-sized operator in Johor will now be measured against it, by regulators and by the communities around their sites.

Johor has also created a state committee that must approve every new data centre before it applies for planning permission. BMI calls Johor the most power-constrained hub in Asia Pacific and estimates its data centres could absorb more than 90% of the new generation added in Peninsular Malaysia over the next five years. The state’s answer is 5 GW of new solar, starting mid-2029. That is a long time to wait if your tenants are already signed.

The Riau corridor I was optimistic about has stalled

A month ago I would have called the Riau Islands Singapore’s future green power factory. I need to revise that.

On 2 November, Indonesia’s energy minister, Bahlil Lahadalia, said Indonesia would not export electricity to Singapore unless the price was right, and that domestic needs come first. This followed piped gas cuts to Singapore from 24 October, accusations about LNG resale, and an escalating dispute over transboundary haze. Indonesia also says its own data centres will need at least 20 GW of low-carbon power. Cross-border sales licences currently run five years. Developers need twenty or more to finance a solar-plus-storage plant.

Singapore has responded the way small, exposed states do. It is diversifying. Sembcorp received conditional approval for 1.3 GW of imports in late October, on top of 900 MW approved from Johor in August, with Vietnam, Australia and Cambodia also in the mix.

None of this means the Riau projects disappear. It means their most natural buyer may change. Batam, twenty kilometres away, has data centres that need clean, firm power and an island grid adding mostly gas. If the export market stays frozen, selling that power locally starts to look less like a fallback and more like the obvious deal.

Batam’s real constraint turned out to be trust

Batam is the place where the gap between announcement and reality is most visible. BP Batam lists ten data centre companies. Developers talk about thousands of megawatts. Yet PLN Batam’s chief executive said this month that actual data centre load is under 50 MW, with fewer than ten companies on supply contracts.

Meanwhile residents near Nongsa Digital Park protested in October and again in early November over prolonged water cuts. The mayor blames drought and El Niño. Residents blame the data centres. Since late September, authorities have required developers to build their own desalination plants for cooling.

Who is right about the cause matters less than the fact that the argument is happening at all. A data centre that cannot explain its water use to the village next door now carries a risk that does not show up in its power purchase agreement.

Indonesia is writing the rules while the concrete is poured

Komdigi has put a draft presidential regulation on submarine cables and data centres out for public consultation, and is pushing private investment towards eastern hubs such as Kupang and Bitung. In Cikarang, meanwhile, STT GDC has energised its own high-voltage substation and is building halls designed for Nvidia’s next platform. The rules and the buildings are being finished at the same time, which is usually when the best and worst deals get made.

What I am watching now

The megawatt used to be a commodity you secured and held. In this market it now comes with conditions attached: a government that wants it paid for, a neighbour who wants to know where the water goes, and a foreign regulator that wants to know who is on the other end of the fibre.

For investors and operators, especially those with Chinese backgrounds, I think this favours a quieter kind of advantage. It belongs to the teams that can tell a credible story about their tenants, their power and their water before anyone asks. It works against those holding idle reservations and hoping the market comes to them.

Over the next few weeks I will be watching whether the US licensing rule is published and how far it reaches, the detail of Malaysia’s 2027 tariff, the Indonesian draft regulation, whether Jakarta and Singapore find a way back to the table on power and gas, and how DayOne’s Nasdaq IPO prices.

If you are building, financing or supplying power to data centres in Johor, Batam or Jakarta, I would like to hear what you are seeing on the ground. What is the question your tenants started asking this quarter that they never asked before?

Sources: The Information via W.Media; Nvidia Form 8-K; The Star and Bloomberg; Malaysian Parliament statements as reported by DC Market Insights; W.Media; FMT and BMI; The Edge Malaysia; Katadata; ANTARA; AFP; CNBC Indonesia; TNGlobal. Figures as of 17 November 2026.